Vigo County Lafayette Avenue

Vigo County Lafayette Avenue

Vigo County, IN

Lafayette Avenue

HWC is responsible for the oversight, and protection of our client: Vigo County, the Indiana Department of Transportation, and FHWA. This includes the full-time inspection, testing, documentation, invoicing, and close-out of the construction operations involved. This LPA project was completed at an estimated cost of $1,059,402.10. Construction was completed in August 2019 with a completion date of June 30, 2020, for the notice of termination. 

Contract was for the widening of this stretch of roadway to accommodate two lanes of traffic with a center turn lane, improving site drainage, updating traffic signal and pedestrian cross walk at the local Junior High School, and reestablishing the southbound turn lane activation loops at the Haythorne Avenue traffic signal.

Bloomington Adams Street Sidewalk & Intersection Improvements

Bloomington Adams Street Sidewalk & Intersection Improvements

Bloomington, IN

Adams Street Sidewalk & Intersection Improvements

HWC is providing full-time inspection for the sidewalk and intersection improvement project along Adams Street from Patterson to Kirkwood.  

This .21 mile long project will allow safer pedestrian and bicycle travel along this corridor by installing planters and other deterrents to protect these pedestrians.

The project is being constructed in four phases to ensure commuter access is maintained throughout construction.  

Other work elements include construction of new sidewalk, installation of a modular block wall, traffic signal modifications at the Adams and Kirkwood intersection, and geometric modifications to accommodate the new bike lanes.  

Construction on the project began in March of 2020 and is expected to be completed in September of 2020. This project is fully funded by the City of Bloomington and is expected to cost $1,259,943.00.

Indianapolis Resurfacing & Related Items in Marion County Area #1

Indianapolis Resurfacing & Related Items in Marion County Area #1

Indianapolis, IN

Resurfacing & Related Items in Marion County Area #1

HWC was responsible for inspection services of the Resurfacing in Marion County Sector 1 project in Indianapolis, Indiana. A total of 33 individual street sections were included in this package.

Project work included replacement of portions of existing curb and gutter, sidewalk, and ADA ramps as well as addition of new sidewalk sections to connect existing to future trails, both asphalt and PCCP base repair, roadway mill and resurface, new and revised sections of pavement markings and areas of full roadway reconstruction.

The project was funded by Indianapolis Department of Public Works for approximately $4.0 million.

Indianapolis Winthrop Avenue

Indianapolis Winthrop Avenue

Indianapolis, IN

Winthrop Avenue

The goal of the Indianapolis DPW – Winthrop Avenue project was to transform the existing street into a new streetscape-style project for local residents and businesses. 

Scope included removal and replacement of existing concrete curbs, sidewalk, ramps, drives and milling, patching, and roadway resurfacing. The project also included updates to the storm sewer system and new inlet and storm pipe installation. The contractor installed a decorative lighting conduit so the neighborhood association could purchase future streetlights to beautify the area. 

This $630,000 project was funded by the City of Indianapolis. 

Bethlehem Nugent Sand & Gravel

Bethlehem Nugent Sand & Gravel

Bethlehem, IN

Nugent Sand & Gravel

HWC is responsible for the full-time inspection of the construction of Camp Creek – Bethlehem Road. This project is 0.665 miles long and is located in Bethlehem, Indiana.

The proposed route is a new segment of road that will connect Camp Creek Road to Bethlehem Road. The proposed road will allow Nugent Sand & Gravel to expand their operations in future years by shifting traffic around their property. At the completion of this project, Camp Creek – Bethlehem Road will be turned over to Clark County and open to through-traffic.

The scope of the project includes clearing the fields and wooded areas within the proposed right-of-way, excavating an existing dirt stockpile, installing drainage culverts and ditches, constructing embankments and side slopes, building and paving the roadway, and installing guardrail, pavement markings, and signage. There is also a four sided concrete box culvert that will be installed at the creek crossing near Bethlehem Road.

Construction on the project began in the summer of 2019. The project was placed on hold through the winter and then construction resumed in April of 2020. The road is expected to be completed in June of 2020.

This project is privately funded by Nugent Sand & Gravel and is expected to cost $1,340,623.55.