Ohio County Bridge #19

Ohio County Bridge #19

Ohio County, IN

Bridge #19

HWC provided part-time inspection for the replacement of Bridge #19.

This project was a two-span bridge project over Arnolds Creek on Stewart Ridge Road in Rising Sun, Indiana. This was a community crossing project that was inspected by HWC and constructed by McAllister Excavating.

The project consisted of constructing two reinforced concrete end bents and one pier along with concrete I beams and an 8” reinforced concrete bridge deck. This project included 400’ of new roadway that led into SR 262. Other project additions included stone shoulders, a new steel bridge rail, and new guardrail.

This project bid for $769,930.27 and was completed on time and under budget.

Utica Old Salem Road Reconstruction

Utica Old Salem Road Reconstruction

Utica, IN

Old Salem Road Reconstruction

HWC provided construction inspection services for the $3.0 million Old Salem Road Reconstruction project in Utica, Indiana.

The project was divided into two phases for utility relocation purposes. The first phase began in May 2017 and encompassed approximately 0.4 miles of the roadwork near the Town of Utica. The second phase began in July 2017 and included the remainder of the project.

The project included excavating the existing road and side slopes, adjusting the horizontal and vertical alignment, and rebuilding the roadway with an improved pavement section. The project also included new curb and gutters through most of the project and storm sewers within the Town of Utica. A four-sided concrete box was also installed at the Lentzier Creek crossing.

White County Bridge #171 Replacement

White County Bridge #171 Replacement

White County, IN

Bridge #171 Replacement

HWC worked with White County to complete the Bridge #171 Replacement project. As part of the project, HWC completed bridge and roadway design, hydraulic analysis, waterway permitting, specifications, utility coordination, right-of-way acquisition, bidding, and construction administration services.

The existing bridge was an 82’ adjacent pre-stressed concrete box beam bridge built in 1969. The bridge had deteriorated to require a 12-ton load limit. Additionally, the roadway width was not sufficient for farm equipment, and the guardrail did not meet current standards. The new bridge included a 98’ multi-beam superstructure with integral end bents for minimized maintenance. The new bridge also included standard bridge railing, guardrail, and a 32’ wide roadway.

The project also included farm field drives for legal drain access in all four quadrants. Utilities were considered throughout the design process to minimize relocation impacts and avoid costly relocation expenses.

New Albany Grid Modernization

New Albany Grid Modernization

New Albany, IN

Grid Modernization

HWC provided design and construction inspection services for the $1.9 million Grid Modernization Project in the Downtown Corridor of New Albany, Indiana.

The project began with a conceptual study that evaluated past recommendations, identified three options for the one-way to two-way grid modernization, and identified three complementary projects for the downtown corridor. HWC studied options for grid corridor modernization, and the chosen option included converting Spring, Market, Elm, Pearl, and Bank streets to two-way traffic. This option manages vehicle patterns, improves access to downtown businesses, calms traffic, improves pedestrian safety, provides bike lanes, and enhances the economic vitality of downtown businesses.

The project included the modernization of 15 traffic signals through the project corridor and upgrades pavement markings and signage for two-way traffic. The identified complementary projects include downtown streetscape improvements, one-way to two-way conversions west of State Street, and a downtown pedestrian bicycle plan.