Bloomington Adams Street Sidewalk & Intersection Improvements
Bloomington, IN
Adams Street Sidewalk & Intersection Improvements
HWC provided inspection for the sidewalk and intersection improvement project along Adams Street from Patterson to Kirkwood in Bloomington, Indiana.
This .21-mile project allows for safer pedestrian and bicycle travel along this corridor with the installation of planters and other deterrents to protect pedestrians.
The project was constructed in four phases to ensure commuter access was maintained throughout construction.
Other work elements included construction of a new sidewalk, installation of a modular block wall, traffic signal modifications at the Adams and Kirkwood intersection, and geometric modifications to accommodate the new bike lanes.
Construction on the project was completed in September of 2020. This project was fully funded by the City of Bloomington at a cost of $1.3 million.