Seymour Burkart Boulevard Phase 1

Seymour Burkart Boulevard Phase 1

Seymour, IN

Burkart Boulevard Phase 1

HWC was responsible for the inspection of the construction of Burkart Boulevard Phase 1. The project consisted of 2.3 miles of new roadway, a bridge over the L&I Railroad, and a multi-use trail located in Seymour, Indiana.

Phase 1 was a new segment of roadway to provide a bypass to Freeman Field from US 50. The scope of this project included clearing of farm fields and some wooded areas, constructing new embankments and roadway, installing drainage culverts and several box culverts. The project has a single-span bridge over the L&I Railroad and a long segment of MSE Wall from each end bent east and west of the railroad and new asphalt pavement with a roundabout at the O’Brien Street intersection. The project has a paved multi-use trail along the entire length of the road. Also included was the installation of guardrail, pavement markings, signage, and lighting at the roundabout.

The contract completion date was October 31, 2021. The $17.3 million LPA project was funded by the City of Seymour and INDOT.

Riley INDOT Asphalt Resurface & Bridge Replacement with Small Structure

Riley INDOT Asphalt Resurface & Bridge Replacement with Small Structure

Riley, IN

INDOT Asphalt Resurface & Bridge Replacement with Small Structure

HWC was responsible for the inspection of the construction of the INDOT Asphalt Resurface and Bridge Replacement with Small Structure project contract (RS-40163). This project was approximately 12 miles long and located in Riley, Indiana on SR 159 from SR 46 to SR 246.

This contract consisted of two projects. The scope of the first project consisted of roadway patching, milling, and resurfacing along SR 159 from SR 46 to SR 246. The scope of the second project consisted of the removal of an existing pipe culvert and installation of a new three-sided box culvert structure near Blackhawk, Indiana on SR 159.

The first project remedied pavement failures that were found along the route due to heavy traffic volumes and heavy vehicles. The second project replaced an older structure to remove the potential for failure in the immediate future.

Construction on the contract began in July of 2020 and was completed in August of 2021.

This project was funded by INDOT and FHWA, and the construction cost was just over $7 million.

Clay County Bridge Replacement On SR 46 Over Killion Ditch

Clay County Bridge Replacement On SR 46 Over Killion Ditch

Clay County, IN

Bridge Replacement On SR 46 Over Killion Ditch

HWC provided full-time inspection on this INDOT on-call project. There were two bridges reconstructed within this one contract.

Work elements encompassed within the first bridge structure included the following:

  • Removal of the existing bridge deck
  • Driving piling and pouring concrete for the construction of new bents and piers
  • Placing new beams, reinforcing steel and concrete for phase 1 at 301’ 6” by 16’ 6” and phase 2 at 301’ 6” by 23’ 10”
  • Constructing new concrete bridge approaches
  • Building up and constructing existing roadway to match the bridge elevation
  • Placing asphalt and pavement markings for both ends of the project
  • Placing seed and planting trees as per plan sheet

The second structure in this contract had the shell piling repainted and the original bridge deck was patched. A thin deck overlay was then placed atop the bridge deck.

This project was completed in June of 2020 at a cost of $4.44 million. 

White County Bridge Rehabilitation #104

White County Bridge Rehabilitation #104

White County, IN

Bridge Rehabilitation #104

HWC was responsible for part-time inspection/construction administration for Bridge #104 on CR 100 E over McKillip Ditch in Monon, Indiana.

The project scope included partial removal of the old structure and partial retrofitting between new bridge members, and reconstruction of existing members.

The work included new steel cross beams and a concrete deck which were fitted to refurbished existing structural members. New riprap was placed under the bridge at both existing abutments and new approach asphalt was placed on either side of the new concrete deck.

The project was 100% funded by White County. The total project cost was $294,000.00.

 

Lake County Bridge #240

Lake County Bridge #240

Lake County, IN

Bridge #240

HWC worked with the City of Hammond on the Lake County Bridge #240 project providing construction inspection services.

The project scope included lining three pipes below the earth filled bridge, milling, and resurfacing. 

Project additions included:

  • Bin wall and backfill
  • Moment slab
  • Sidewalks
  • Curbs
  • Bridge railing
  • Lighting
  • Pavement markings