Anderson Mays Park
Anderson, IN
Mays Park
Princeton Water Treatment & Storage Facilities Improvements
Princeton, IN
Water Treatment & Storage Facilities Improvements
HWC first completed a Preliminary Engineering Report for the City’s water treatment and storage systems. Princeton’s water plant was nearly 25 years old and operating nearly 24 hours per day to meet demand. The system also lacked adequate storage volume, had an existing elevated tank in poor condition, and lacked necessary fire protection.
Report recommendations included:
- A 500,000 gallon elevated water tank and 5,000’ of 16” water transmission main
- New aerators and installation of a third aerator/detention basin
- New vertical treatment pumps with variable frequency drives
- A 500,000 gallon ground storage tank and high service pumping station
- A new backwash waste holding basin
- A new SCADA controls system
- Miscellaneous building modifications
HWC completed all planning, design, bidding, and construction management phases for this $4.5 million project.
Lafayette Vinton Subdivision Water Main Replacement
Lafayette, IN
Vinton Subdivision Water Main Replacement
This water main replacement project consisted of installing new 8’’ DIP throughout the subdivision. 5,269’ in total were installed along with 132 new service lines from the new main to the existing meter pit.
The contractor installed the new 8’’ DIP water main with the corporations installed so they could hydrostatic pressure test the new main and the new corporations jointly. The contractor performed many hydrostatic pressure tests and bacteria tests which HWC oversaw.
The contractor installed 8 new hydrant assemblies throughout the subdivision and removed 3 old hydrant assemblies.
Indianapolis DPW/Citizens Energy Group– Lift Station 507 Upgrade
Indianapolis, IN
Citizens Energy Group/DPW – Lift Station 507 Upgrade
The scope of the project included renovating and upgrading existing wet weather storage and pumping facility to allow for enhanced treatment of CSO events. The work required the addition of a self-cleaning screening system, a sodium hypochlorite disinfection system, dechlorination with sodium biosulfate, and necessary chemical storage. The washdown system was replaced with a tipping bucket system. Additional work included sluice gates, structural improvements, 1,000 GPM dewatering pumps, flow/level sensors, backup generator, new SCADA, and electrical/power components. The renovation included the installation of a green roof and miscellaneous site improvements. Significant coordination was required with the Riviera Club due to their normal activities and children present throughout the duration.
The work was required as a part of the City’s CSO Long Term Control Plan program.
The project was, in part, funded by the State Revolving Loan Fund 100%. Construction cost was approximately $4,800,000.00.
Recent Comments