Jasonville Shakamak State Park Regionalization & Wastewater System Improvements

Jasonville Shakamak State Park Regionalization & Wastewater System Improvements

Jasonville, IN

Shakamak State Park Regionalization & Wastewater System Improvements

HWC completed a Preliminary Engineering Report (PER) for funding through the Indiana Finance Authority (IFA)’s State Revolving Fund (SRF) Program for this project. The PER was prepared to address several needs including:

  • Significant inflow and infiltration in the Shakamak State Park collection system
  • Aging and deteriorating equipment and controls at the Shakamak Wastewater Treatment Facility (WWTF)
  • Alleviating DNR from having to operate a wastewater treatment facility
  • Addressing the hydraulic capacity issues and difficulty in meeting ammonia limits at Jasonville’s existing WWTF

To address the needs discussed above, the recommended project in the PER includes Shakamak State Park collection system rehabilitation, wastewater conveyance infrastructure from Shakamak State Park to the City of Jasonville’s WWTF, and upgrades to Jasonville’s existing WWTF. The Shakamak State Park collection system improvements include gravity sewer rehabilitation, consisting of lining approximately 3,745 LF of gravity sewer mains via Cured-In-Place Pipe (CIPP) along with other miscellaneous repairs and upgrades to the Park’s collection system. The wastewater conveyance improvements include upgrading Shakamak’s existing Lift Station Number Five with new pumps and installing approximately three miles of force main from the lift station to Jasonville’s WWTF for treatment along with decommissioning Shakamak’s existing WWTF. The improvements to Jasonville’s WWTF include removal of the lagoon cover system, installation of a new Submerged Attached Growth Reactor (SAGR) Treatment System, and additional wet weather flow storage.

The project has been bid and is expected to be completed in 2024. The construction cost is $8.2 million.

New Albany Wet Weather Clarifier System Improvements

New Albany Wet Weather Clarifier System Improvements

New Albany, IN

Wet Weather Clarifier System Improvements

HWC worked with the City of New Albany, Indiana to complete their Wet Weather Clarifier System Improvements project.

The City of New Albany operates a 30 MGD treatment facility with discharge to the Ohio River. Due to excessive wet weather flows from the separate sanitary sewer system, flow rates up to 75 MGD are conveyed to the treatment facility. A passive overflow structure downstream of three oxidation ditches allows flows of up to 30 MGD to be conveyed to secondary clarifiers while excess flows are diverted to the wet weather clarifiers with an overall capacity of 48 MGD. There are six wet weather clarifiers with circular clarifier mechanisms in square concrete tanks along with all associated piping and equipment. The condition of the clarifiers had depreciated along with the RAS/WAS pumping systems and disinfection facilities for the wet weather flow train, such that the City desired to develop a plan to rehabilitate the wet weather clarification systems.

HWC was retained to develop a basis of design study for the wet weather processes and equipment for developing a final scope of work and budget for the proposed project. The resulting plan evaluated several different alternatives, including complete replacement of all systems with various clarifier tank layouts.

Based on budgetary considerations and the frequency of use of the wet weather clarification system, the selected plan included rehabilitation of the existing systems and equipment. The total project cost was approximately $1.75 million with construction completed in 2019. HWC provided planning, design, bidding, and construction engineering/inspection services for the project.

HWC’s Project Manager was Jon Query, PE.

VanBibber Lake Conservancy District Water System Improvements

VanBibber Lake Conservancy District Water System Improvements

Van Bibber Lake, IN

Conservancy District Water System Improvements

The Van Bibber Lake Conservancy District completed significant improvements to their water system in 2023. The $9.4 million project includes construction of a new water treatment facility and complete replacement of their distribution system. The new water treatment facility included an aerator with detention tank, new vertical pressure filters, and new building in order to reduce the very high levels of iron in the raw water. The new water distribution system included installation of 24,000’ of new 6” and 4” water main to replace the undersized and failing water mains under homes and structures. The project also included the installation of 430 new AMI water meters since the system was previously unmetered at each residence. This project will improve the water quality, pressure, and flow to all the residents of the Van Bibber Lake community. The project was funded with an Indiana Office of Community and Rural Affairs (IOCRA) grant, Indiana Finance Authority (IFA), State Revolving Fund (SRF) forgivable loan, and United States Department of Agriculture (USDA) Rural Development loan and grant.

Veedersburg Wastewater System Improvements 

Veedersburg Wastewater System Improvements 

Veedersburg, IN

Build-Operate-Transfer (BOT) Wastewater System Improvements

The Veedersburg Wastewater System Improvements project included improvements to the existing Wastewater Treatment Plant (WWTP) to improve overall efficiency of the treatment system and update critical pieces of equipment. The project included replacement of the antiquated aerated lagoon “biolac” treatment system with a new oxidation ditch and two secondary clarifiers, a new influent structure, replacement of the existing UV treatment system with a non-contact type UV system, post-aeration, conversion of the existing north clarifier to a digester, and various improvements to electrical and controls. In addition, the project included the replacement of five lift stations (Primary, Sherman Street, Main Street, College Street, and Viewer Hills) located throughout the Town of Veedersburg to replace deteriorated facilities and improve the operation and efficiency of the collection system.  The project utilized the Build-Operate-Transfer (BOT) delivery method and was funded in part by the State Revolving Fund (SRF) program.

The $9.5 million project was completed in the fall of 2023.

Attica CSO LTCP Phase II/Wastewater Treatment Facility Renovation

Attica CSO LTCP Phase II/Wastewater Treatment Facility Renovation

Attica, IN

CSO LTCP Phases 2/Wastewater Treatment Facility Renovation

HWC worked with Attica, Indiana to complete Phase 2 of the City’s mandated CSO LTCP project. 

The City’s CSO Long-Term Control Plan required a second and final phase, which included floatables screening of flows from the single remaining overflow outfall to remain operational and storage of approximately 750,000 gallons of combined sewer flows to meet IDEM’s design storm criteria. HWC was hired to develop a Preliminary Engineering Report for the CSO project and necessary improvements at the treatment facility to address depreciation and compliance needs. 

The plan developed included improvements at the treatment facility, including:

  • New influent/CSO screening structure, which complied with the floatables control requirement of the CSO LTCP and fine screening for all influent flows
  • New 750,000 gallon per day average flow/1.2 MGD peak flow oxidation ditch for biological treatment to replace the current trickling filter process
  • Conversion of existing primary clarifiers to secondary clarifiers
  • Conversion of the existing trickling filter tanks to CSO storage tanks, which will be filled by dedicated CSO pumps in the retrofitted influent wet well
  • Chemical feed systems and piping for nutrient (phosphorus) control
  • Implementation of a new plant-wide SCADA system for both biological and wet weather process control

Due to the re-utilization of existing structures and conversion to a new biological treatment process, significant construction sequencing considerations were required in the design of the project. HWC held working sessions with the plant staff during design and with both the contractor and staff during construction to ensure minimization of operational disruptions were realized through demolition and sequencing of construction activities.

The total project cost was approximately $5.5 million. HWC provided planning, design, construction engineering, and inspection services for the project.